Execute On schedules the Job at a specific future date and time.
To learn about Job Designer, let us walk through the below procedure:
- Click on BATCH CONSOLE module.
- Hover and click on Job Designer snippet.
- A Job Designer session page is displayed.
- From the Schedule tab, let’s drag and drop Execute On icon onto the Job Designer session page and double tap on it.
- An Execute On pop-up window is displayed.
- Let’s add the desired Start Date and Start Time as per the requirement.
- The Execute on: 30/01/2023, at 00:44 Schedule Summary is updated accordingly.
- Click on Save button to save the widget.
- Click on the Objects tab.
- Let’s, drag and drop FDR Scenarios icon onto the designer page and double-tap on it.
- An FDR Scenario2 pop-up window is displayed.
- Let’s select the required FDR scenarios.
- Click on Select button.
- The Job Designer page is displayed.
- Let’s, drag and drop Validation Scenarios icon on to the designer page and double tap on it.
- A Validation Scenario 3 pop-up window is displayed.
- Click on Select to save the Validation Scenario 3 widget.
- We will be navigated to the Job Designer page.
- Click on Additional Options tab.
- Let’s, drag and drop an Email (Overall) icon and double-tap on it.
- An Email (Overall) 4 pop-up window is displayed.
- Click on Save button to save the widget.
- We will be navigated to the Job Designer page.
- Click on Save Schedule icon.
- This action navigates to the Job Explorer
- Click the Scheduled option.
- Search with scheduling Job and here we can view our job scheduled using Execute On option.